Technical Due Diligence

Technical Due Diligence

Due Diligence Simulus Engineers have completed over 120 due diligence reviews and project assessments. The breadth of these assessments over the last 10 years isĀ amazing. We have completed reviews and assessments for financial institutions, private equity funds,...
Copper plant commissioning

Copper plant commissioning

Simulus Engineers provided on site lead process engineering for construction completion verification, commissioning, debottlnecking and ramp up for the Mutanda copper/cobalt project. The Mutanda project processes 2.5Mt/a ore to produce 200,000 t/a copper cathode and...
Heron CFNP scoping study

Heron CFNP scoping study

Simulus Engineers provided engineering scoping studies to Heron for 10kt/a and 20 kt/a nickel production utilising the patent CFNP process, which reduces net acid demand by 60-80% and in turn increases project NPV by up to 100%.